Simandou Site Facilities

Design and construction of the temporary site facilities that support Rio Tinto's Ouéléba mine and 60 Mtpa iron ore plant at Simandou: offices, warehouse, laboratory, infirmary, power and water.

Ref. I0016-1100-MSA-CON-097.3

Client

Rio Tinto Simfer

Funding

Rio Tinto Simfer

Location

Beyla, Guinea

Period

In progress

Sector

Construction et infrastructures

Reference

I0016-1100-MSA-CON-097.3

The Project

The Simandou South mining project lies about 550 km east-south-east of Conakry, towards the southern end of the 110 km Simandou range, within SIMFER's mining concession. Its two iron ore deposits, Pic de Fon to the south and Ouéléba to the north, sit about 4 km apart along the ridgeline. Each is about 7.5 km long and up to 1 km wide.

The mine is being developed together with new rail and port infrastructure. To prepare it, Rio Tinto launched a series of construction projects across the site, including this temporary site facility, delivered by IBS Group.

Capacity of the iron ore plant the facility serves
0 Mtpa
From Conakry
0 km
Facility packages in the scope
0

Scope of work

The camp pad itself is built by others: a platform of at least 15 hectares with a minimum 2% cross-fall. IBS Group delivers everything on it.

Business buildings: office, ablutions, warehouse, laboratory

Company parking and drop-off area

Infirmary facilities

Start-up and drop-off areas for contractors' heavy vehicles

Security cabin and bus loading bay

Civil and structural works, including concrete slabs and lawns

Low-voltage power: solar array, battery storage, generator and on-site distribution

Water services: rainwater harvesting, storage tanks, pumps, ablution sanitation, septic tank and wastewater disposal

Soft-shell satellite canteens

Prayer room

Temporary emergency facility